CONTENTS 1.Introduction 2.Contract Management 3.Risk Management 4.HSE Management 百年同濟2
2 1. Introduction 2. Contract Management 3. Risk Management 4. HSE Management CONTENTS
1.Introduction Owner's Tunneling Project Management Designer's Tunneling Project Management Contractor's Tunneling Project Management 百年同濟 3
3 1. Introduction Owner’s Tunneling Project Management Designer’s Tunneling Project Management Contractor’s Tunneling Project Management
1.Introduction Owner's Tunneling Project Management: Owner decides with advice from others 1)On the form of procurement 2)Who will design the works 3)Form of contract 百年同濟4
4 1. Introduction Owner’s Tunneling Project Management: Owner decides with advice from others • 1) On the form of procurement • 2) Who will design the works • 3) Form of contract
1.Introduction Owner's Tunneling Project Management: Pre-Bidding Documents Geological and geotechnical data as much as possible Full disclosure of all GG data Geological model GG Data Report Geotechnical Base Report 百年同濟 5 TONGILUNIVERSITY
5 Pre-Bidding Documents Geological and geotechnical data as much as possible Full disclosure of all GG data • Geological model • GG Data Report • Geotechnical Base Report 1. Introduction Owner’s Tunneling Project Management:
1.Introduction Owner's Tunneling Project Management: Role of Contracts Keep fair balance among quality,schedule and costs Mix of technical and performance specifications> quality control Independent auditing and full disclosure of control parameters Incorporate risk management and risk sharing 百年同海6
6 Role of Contracts Keep fair balance among quality, schedule and costs Mix of technical and performance specifications quality control Independent auditing and full disclosure of control parameters Incorporate risk management and risk sharing 1. Introduction Owner’s Tunneling Project Management: